Bradeney House
Installation of new Sewage Treatment Plant
AGH Contract Services secured the contract to install a new sewage treatment plant system for Bradeney House nursing & care home, located in Worfield, Bridgnorth.
The scope of work included:
-
Excavate ground to reduce levels
-
Lay strip foundations
-
Excavate and install 2-stage Primary Settlement Tank
-
Excavate and install Humus settlement tank
-
Lay new foul drain to new package treatment plant
-
Excavate drain trench for pipes
-
Lay new surface water drains to new soakaways
-
Build manholes - complete with covers
-
Deposit excavated material on site
-
Re-instate ground
-
Arrange commission of plant, etc