Bradeney House

Installation of new Sewage Treatment Plant

AGH Contract Services secured the contract to install a new sewage treatment plant system for Bradeney House nursing & care home, located in Worfield, Bridgnorth. 

The scope of work included:

  • Excavate ground to reduce levels

  • Lay strip foundations

  • Excavate and install 2-stage Primary Settlement Tank

  • Excavate and install Humus settlement tank

  • Lay new foul drain to new package treatment plant

  • Excavate drain trench for pipes

  • Lay new surface water drains to new soakaways

  • Build manholes - complete with covers

  • Deposit excavated material on site

  • Re-instate ground

  • Arrange commission of plant, etc

 

1/4